Heat Exchanger Tubing Eddy Current (ECT/RFT/IRIS) Guide
Field Procedure for ASME Section V Article 8 & TEMA RCB Defect Sizing
Key Technical Takeaways & Execution Rules
- Set bobbin probe test frequencies so differential signal phase angle for 100% through-wall through-hole is set between 40° and 50° (standard 4-channel setup).
- Calibrate depth curves using ASME Section V Article 8 calibration standard with 20%, 40%, 60%, 80% OD flat-bottom holes (FBH) and 20% ID circumferential groove.
- For carbon steel and ferromagnetic tubing, transition from standard ECT to Remote Field Testing (RFT) or Internal Rotary Inspection System (IRIS) ultrasonic probes.
- TEMA Section 5 RCB requires mandatory tube plugging when remaining wall thickness drops below the calculated minimum pressure threshold (typically >=60% wall loss).
Step-by-Step Field Execution Procedure
Bobbin Probe & Fill-Factor Verification
Select differential/absolute bobbin probe with a fill-factor between 0.80 and 0.85 (probe OD = 0.8 to 0.85 * tube nominal ID) to ensure maximum sensitivity without binding on tube scale.
ASME Reference Standard Calibration & Phase Freeze
Pull probe through ASME Section V Article 8 calibration tube. Adjust phase angle so horizontal movement represents probe wobble. Lock through-hole signal at 40° in quadrant 1.
Phase-to-Depth Calibration Curve Generation
Record signal amplitudes and phase rotations from 20%, 40%, 60%, and 80% OD flat bottom holes. Generate phase angle vs. depth calibration curve inside the data acquisition software.
High-Speed Automated Bundle Raster Acquisition
Execute automated tube pulling using a pneumatic pusher-puller at 1.0 to 1.5 m/s. Flag tube sheet rollovers, baffle support wear plates, and free-span pitting.
Tubesheet CAD Mapping & Plugging Determination
Import inspection matrix directly into TEMA Tube Designer CAD. Map percent wall loss, identify clusters of tubes requiring tapered ASME plugs, and export client tubesheet map.
Governing Physical & Code Formulas
Standard Depth of Penetration (Eddy Current Skin Depth)
Code FormulaDetermines the test frequency required for eddy currents to penetrate through tube wall thickness to resolve outer diameter (OD) defects.
TEMA RCB U-Tube Bending Thinning Allowance
Code FormulaCalculates the mandatory minimum pre-bent tube wall thickness required to ensure bends do not breach minimum pressure limits.
Probe & Wedge Selection Specs
- Bobbin Differential (Air-Core)
- RFT Dual-Driver Bobbin
- IRIS Ultrasonic Turbine Head
Code Acceptance Criteria
ASME Sec VIII Div 1 / TEMA RCB: Wall loss exceeding 60% requires mechanical or explosive tapered plugging. Wall loss between 40% and 59% is recorded on tube inspection sheet for 2-year trending.