ASME Boiler & Pressure Vessel Code (BPVC) & NDT Examination Guide
Comprehensive reference catalog for ASME Section V (Nondestructive Examination), ASME Section VIII (Pressure Vessels), ASME B31 Process & Power Piping Codes, Section IX Welding, and PCC-2/FFS-1 Post-Construction integrity rules.
Explore API standards (510/570/653) cross-referenced with ASME Section V NDE calibration and acceptance criteria.
Ultrasonic Examination Methods for Welds
Always calibrate sweep and DAC curves on a NIST block within 25°F (14°C) of the test part before taking field readings.
- T-420 General Examination Requirements & Equipment Qualification
- T-434 Calibration Blocks (P-Numbers & Thickness Ratios)
- +3 additional mandatory sections
Radiographic Examination (RT & CR/DR)
Film density must stay strictly between 1.8 and 4.0 H&D, and the designated IQI wire must be clearly visible across the weld area.
- T-220 General Requirements & Radiation Source Selection
- T-233 Image Quality Indicators (Hole-type & Wire IQIs per ASTM E747)
- +3 additional mandatory sections
Surface Examination: Liquid Penetrant (PT) & Magnetic Particle (MT)
Magnetic yokes must easily lift a certified 10 lb steel weight (AC) or 40 lb weight (DC) before starting inspection.
- Art. 6 T-640 Penetrant Materials & Dwell Times (5 to 30 mins)
- Art. 6 T-676 Interpretation & Temperature Range (40°F to 125°F)
- +2 additional mandatory sections
Eddy Current Examination (ET) of Nonferrous Heat Exchanger Tubing
Any tube with greater than 50% wall loss is typically slated for tube plugging or bundle re-tubing.
- T-820 Equipment Specifications & Multi-Frequency Mix Calibration
- T-830 Calibration Reference Standards (ASME Sec V Art 8 Standards)
- +2 additional mandatory sections
Leak Testing Methods (LT)
Maintain minimum 20 inHg vacuum for at least 15 seconds over each weld seam with overlapping inspection boxes.
- T-1030 Direct Pressure Bubble Test (Solution Application)
- T-1040 Vacuum Box Test Method for Tank Bottoms & Flat Surfaces
- +1 additional mandatory sections
Rules for Construction of Pressure Vessels
Full RT allows 100% joint efficiency (E=1.0) so tank walls can be thinner, while Spot RT requires thicker walls (E=0.85).
- UG-93 NDE Requirements for Plate & Forgings
- UW-51 Full Radiographic Examination & Ultrasonic Acceptance Criteria
- +3 additional mandatory sections
Pressure Vessels: Alternative Rules (Design by Analysis)
Requires 100% volumetric inspection (PAUT/TOFD) on all main pressure welds with zero tolerance for crack-like flaws.
- Part 7: Examination Requirements & Acceptance Standards
- Section 7.5: Volumetric Examination (Phased Array UT & TOFD)
- +1 additional mandatory sections
Rules for Construction of Power Boilers
Steam drum longitudinal seams must have 100% volumetric testing, with hydrotest pressure set to 1.5x design pressure.
- PG-90 Inspection & Examination Provisions
- PW-11 Radiographic Examination of Butt Welded Joints
- +1 additional mandatory sections
Process Piping Code (Petrochemical & Refineries)
Normal fluid service requires 100% visual and random 5% radiography, while Severe Cyclic requires 100% volumetric inspection.
- Chapter VI: Examination, Inspection, and Testing
- Paragraph 341.4: Extent of Required Examination (Visual 100%, Volumetric 5% to 100%)
- +2 additional mandatory sections
Power Piping Code (Electric Power Stations)
Steam lines operating over 750°F or 100 psi mandate 100% volumetric radiography or ultrasonic examination.
- Chapter VI: Inspection, Examination, and Testing
- Paragraph 136: Mandatory NDE Extent (100% RT/UT for steam lines > 100 psi / > 750°F)
- +1 additional mandatory sections
Pipeline Transportation Systems (Liquid Hydrocarbons & Gas Transmission)
Class 3 and Class 4 high-consequence locations require 100% radiography or AUT girth weld inspection.
- B31.4 Chapter VI: Inspection and Testing
- B31.8 Chapter IV: Operating and Maintenance Procedures (Integrity Management)
- +1 additional mandatory sections
Rules for Inservice Inspection of Nuclear Power Plant Components
All automated and manual ultrasonic examiners must be qualified on blind nuclear mockups per Appendix VIII.
- Subarticle IWA-2200 Examination Methods (Visual VT-1, VT-2, VT-3, Surface, Volumetric)
- Appendix VIII: Performance Demonstration for Ultrasonic Examination Systems (PDI Qualified Examiners)
- +1 additional mandatory sections
Welding, Brazing, and Fusing Qualifications
Zero tolerance for cracks, lack of fusion, or lack of penetration on welder qualification test coupons.
- QW-191 Radiographic and Ultrasonic Examination of Welder Qualification Coupons
- QW-300 Welder Qualification Standards
- +1 additional mandatory sections
Repair of Pressure Equipment and Piping
Insert plate flush welds must have rounded corners (minimum 1 in radius) and 100% volumetric inspection.
- Article 201: Butt-Welded Insert Plates in Pressure Components
- Article 401: Non-Metallic Composite Repair Systems for Pipelines & Piping (ISO 24817 / ASME PCC-2)
- +1 additional mandatory sections
Fitness-For-Service (FFS Evaluation)
Level 1 is a quick spreadsheet screening; Level 2 uses detailed profile thickness grids; Level 3 requires finite element stress analysis.
- Part 4: Assessment of General Metal Loss (Grid UT Data)
- Part 5: Assessment of Local Metal Loss (High-Resolution NDT Mapping)
- +1 additional mandatory sections
Need Level III Examination Procedures or Calibration Standard Blocks?
ASME Section V requires written examination procedures qualified per Article 1 & Article 4 (PAUT/UT), Article 2 (Radiography), and Article 8 (Eddy Current). Calibration blocks must strictly mirror component P-numbers and nominal wall thicknesses.
ASME vs. API Code Relationship
API in-service inspection codes (API 510, API 570, API 653) rely directly on ASME Section V for mandatory NDT examination procedures, and ASME Section VIII / B31.3 for rerating calculations.