API 570 Process Piping Circuit & Dead-Leg Inspection Scope
Ultrasonic Thickness Baseline, Injection Point CMLs & Digital Radiography
Primary NDT Techniques:UTCRPAUT
Targeted Damage Mechanisms
- Microbiologically Induced Corrosion (MIC) in Deadlegs
- Flow-Accelerated Corrosion (FAC) at Elbows
- Hydrochloric Acid Pitting at Injection Points
Key Inspection Challenges Resolved
- Dead-legs collect stagnant water and corrosive sediment that accelerate internal wall loss exponentially.
- Turbulence downstream of injection points causes localized flow-accelerated erosion-corrosion.
- Active piping operating at temperature cannot be shut down for testing.
Standard Field Inspection Workflow
1
Isometric Circuit & CML Register Review
Walk down piping isometrics to verify condition monitoring locations (CMLs), injection points, and dead-leg low-point drain branches.
2
Computed Radiography Profile Shots
Execute tangential digital radiography (CR/DR) on injection point quills, socket welds, and small-bore branch connections without insulation removal.
3
High-Temperature Grid UT
Deploy high-temperature delay-line transducers to measure 4-point quadrant wall thicknesses around 90° elbows and downstream tees.
4
API 570 Corrosion Rate & RL Analysis
Compare current thickness readings against historical baseline to calculate Short-Term (ST) vs. Long-Term (LT) corrosion rates and next half-life date.
Recommended Hardware & Probes
- Carestream HPX-1 Plus CR Scanner
- Olympus 38DL Plus High-Temp Dual-Element Gauge
- Eddyfi Lyft PEC
Governing Inspection Standards
- API 570 Piping Inspection Code
- ASME B31.3 Process Piping
- API RP 574 Inspection of Piping System Components
Turnaround Operations & Site Prep
Typical Outage Duration:Ongoing Campaign or 5-Day Outage Sweep
Recommended Crew Roster:1× API 570 Certified Inspector, 2× Advanced Ultrasonic Technicians, 1× Radiography Crew (Level II + Assistant)
Pre-Requisite Site Prep & Safety:
- Piping CML tags stamped or clearly marked with paint markers
- Insulation inspection ports (plugs) installed at CML locations
- Radiation boundary barricades coordinated for tangential shots
Certified Deliverables & Sign-Offs
- Piping Isometric CAD Overlay with Tagged CML Thicknesses
- Tangential Digital Radiography Images with Wall Caliper Measurements
- API 570 Remaining Life & Minimum Thickness (t_min) Calculation Table
- Immediate Piping Replacement Work Order for Sub-t_min Spools