Turnkey Inspection Projects Showcase

5-Tier Operational Lifecycle Architecture

Explore verified turnkey project case studies demonstrating asset hierarchies, 3D digital twins, ray tracing scan plans, and signed Level III inspection reports.

CERTIFIED DELIVERABLE REPORTCompleted & SignedDOC #EXCHANGER-TEMA-2026

FCCU Overhead Condenser Tube Bundle Inspection

Browse Live RFPs

Initiation

Bidding

Execution

Completion

Completed

Next Step for Client

Project status monitoring active.

Turnkey Scope RFPFixed-Bid Scope ($24,000 Fixed RFP)4 Days Emergency Shutdown

Project Specification & Asset Overview

Launch TEMA Tubesheet Designer
Code Specs & Regulatory Standards ISO 17025 Calibrated
ASME Sec VIII Div 1 / TEMA RCBASME Sec VLevel III Approval Required

Project Description

100% full bundle screening (1,240 tubes) identifying OD baffle wear, ammonia-induced wall thinning, and tube-to-tubesheet seal integrity.

Target Asset

Exchanger Bundle E-201 (1,240 Tubes, Titanium Gr 2)

Asset Category

Shell & Tube Heat Exchanger Bundle (3/4" OD × 18 BWG)

Client Industry

Petrochemical Hydrocracker Unit

Turnkey Fixed Budget

$24,000 Fixed RFP

Mobilized Inspection Fleet & Calibrated Hardware

Eddyfi Ectane 2 Multi-Technology + IRIS Rotary Ultrasonic Probe

5-Tier Work Breakdown Structure

Interactive operational tree: Project → Asset → NDT Techniques → Inspection Logs.
Exchanger Bundle E-201 (1,240 Tubes, Titanium Gr 2)Shell & Tube Heat Exchanger Bundle (3/4" OD × 18 BWG) • ASME Sec VIII Div 1 / TEMA RCB
Completed
Eddy Current (ECT)Governing Spec: ASME Sec VIII Div 1 / TEMA RCB • 100% Calibrated
Completed
Internal Rotary IRISGoverning Spec: ASME Sec VIII Div 1 / TEMA RCB • 100% Calibrated
Completed
Remote Visual (RVI)Governing Spec: ASME Sec VIII Div 1 / TEMA RCB • 100% Calibrated
Completed
Magnetic Saturation (MFL)Governing Spec: ASME Sec VIII Div 1 / TEMA RCB • 100% Calibrated
Completed