Desulfurization Hydrotreater Reactor Vessel Inspection
Comprehensive internal & external baseline inspection of thick-wall hydrotreater vessel evaluating 2:1 ellipsoidal head MAWP, nozzle reinforcement zones, and hydrogen damage micro-fissuring.
Hydrotreater Pressure Vessel V-101 (2:1 Ellipsoidal Head)
Thick-Wall Clad Pressure Vessel (4.2m Dia × 26m Height, 185mm Wall)
High-Conversion Oil Refinery
API 510 / ASME Sec VIII Div 1 / API 941
Evident OmniScan X3 64:128 + Olympus RollerFORM 2 + Phoenix MagMan Scanner
6 Days Turnaround Window
Initiation
Completed
Bidding
Completed
Execution
Completed
Completion
Completed
Hydrotreater Pressure Vessel V-101 (2:1 Ellipsoidal Head)
Thick-Wall Clad Pressure Vessel (4.2m Dia × 26m Height, 185mm Wall) • API 510 / ASME Sec VIII Div 1 / API 941 • High-Conversion Oil Refinery